Appendix D: Capacity Management : Organization Virtual Datacenter-Specific Capacity Forecasting : Determine Trending Variables
   
Determine Trending Variables
With the information recorded as described in the following table it is possible to determine the rate of organization virtual datacenter consumption.
Table 16. Organization Virtual Datacenter Capacity Trending Variables
Variable
Name
Description
Units
T
Time
Time between points of observation.
Weeks
NcpuUC
New CPU Units
Total number of CPU units of consumption required for the forecasted virtual machines.
CPU units of consumption
NmemUC
New Memory Units
Total number of memory units of consumption required for the forecasted virtual machines.
Memory units of consumption
NVGB
New Storage (GB)
Total amount of storage required for the forecasted virtual machines.
GB
Tpurchase
Organization Virtual Datacenter Expansion Purchase Time
Amount of time to procure additional organization virtual datacenter resources.
Weeks
 
Determining the Trended Growth Rate
 
Determining the Trend
It is important to understand that the rate of increase dictates how far in advance additional organization virtual datacenter resources need to be purchased. The following table presents a sample virtual machine forecast for a quarter along with sample time-to-purchase value.
Table 17. Sample Organization Virtual Datacenter Trending Information
Attribute
Value
ΔNcpuUC
12
ΔNmemUC
12
ΔNVGB
360GB
Tpurchase
2 weeks
NcpuUC,cluster
320
NmemUC,cluster
717
 
In the following example, NcpuUC,free and NmemUC,free represent the number of free resources within an organization virtual datacenter at which point additional organization virtual datacenter resources should be ordered.
To determine the trigger point for ordering, use the following equation if no pipeline data exists.
Determining Trigger Point for Ordering Capacity Using Trends
For example, from the data provided below, one can calculate the needed free consumption units as listed in the following equation, or 24 units.
For storage, in this example, the trigger point is calculated at 720GB: