Appendix D: vCloud Director Upgrade Considerations : Phase 1 Process : Pre-Upgrade Considerations : Upgrade Considerations
   
Upgrade Considerations
The following guidelines list the key steps to perform during an upgrade.
Table 28. Upgrade Procedure
#
Component
Consideration
Resource
1
VCD Cells
*Suspend VCD scheduler and stop VCD service.
*Repeat for subsequent cells.
*Perform Red Hat patches.
*Un-mount the NFS transfer share on each cell.
*Run the vCloud Director installer but do not start the services.
*Run the database upgrade script on the first cell only. Do not repeat this on the other cells.
*Run the vCloud Director installer on the other cells.
*Reboot each VCD cell one at a time to make sure that all services start up correctly and that the NFS transfer volume is successfully mounted on the first cell before rebooting subsequent cells.
*Validate that vCloud Director has started by checking /opt/vmware/vcloud-director/logs/cell.log.
*Validate that the portal is working on each cell by connecting directly to the cell’s HTTP interface.
*Do not redirect the load balancer or allow users back onto the system yet.
vCloud Administrator
 
Linux Administrator
vCloud Administrator
vCloud Administrator
 
vCloud Administrator
vCloud Administrator
 
vCloud Administrator
vCloud Administrator
2
Update VCD Agent on vSphere hosts
Update the host agent on all connected hosts. Check that connected hosts are still showing Available and Prepared.
vCloud Administrator
3
VCD Validation 1
*Validate basic functionality of VCD by deploying a new vApp.
*Validate basic functionality by deploying a NAT routed network (either a routed organization network or fence a vApp that is deployed).
*Troubleshoot any issues before moving on.
*Rollback is possible at this stage by restoring the VCD database and restoring the VCD cells virtual machine backup or deleting the virtual machine snapshot.
vCloud Administrator
vCloud Administrator
 
 
vSphere Administrator or Database Administrator
4
vCloud Networking and Security Manager Server
Upgrade of the vCloud Networking and Security Manager Server requires the use of an upgrade package. This file is usually named VMware--Manager-upgrade-bundle-5.1.0-.tar.gz.
Do not deploy a new VMware Service Manager appliance (OVA).
Removing the existing Service Manager appliance breaks all connections and management to any deployed vCloud Networking and Security Manager Edge devices, resulting in errors. After a Service Manager is deployed, it should only be upgraded using a tar.gz file (in place upgrade). This preserves the local Service Manager database.
vCloud Administrator
5
Edge devices
After vCloud Networking and Security Manager has been upgraded, wait at least 15 minutes for it to update information with VCD.
Upgrade any organization vCloud Networking and Security Manager devices – any Manager that is connected to an organization network that is routed. These devices are identified in VCD 5.1 as Edge Gateways and can be upgraded by performing Re-Deploy.
Upgrade any vApp network vCloud Networking and Security Manager devices – any Manager that is connected to an vApp network that is routed. These devices are identified in VCD 5.1 as Edge Gateways and can be upgraded by performing Re-Deploy.
 
 
vCloud Administrator
 
vCloud Administrator or Organization Administrator
6
VCD Validation 2
*Validate basic functionality of VCD by deploying a new vApp.
*Validate basic functionality by deploying a NAT-routed network (either a routed organization network or fence a vApp that is deployed).
*Troubleshoot any issues before proceeding.
*Rollback is not possible at this stage as VSEs have been upgraded to the latest compatible versions.
vCloud Administrator
vCloud Administrator
7
Chargeback Managers
The installer requires that the previous version be uninstalled. Select Do not empty the database.
vCloud Administrator